Showing posts with label foundation work. Show all posts
Showing posts with label foundation work. Show all posts

20 August 2009

new doors and floors

Last week our concrete slab at the garden level floor was poured. What a difference to walk downstairs and see concrete.






We also had all of our doors delivered last week. At 7'-6" tall and usually 3'-0" wide they are truly stunning. Here is a pair of doors that will get installed on the parlor floor.
Work also continues on the parlor floor stair opening which looks down to the kitchen on the garden floor.

Next week a whole team of sheetrockers are scheduled to close the rest of the walls up throughout the townhouse. This means no more visible plumbing in the bathrooms and much more running millwork and trim up in the house.
In preparation the team has added firestopping at all floors around the pipe runs. It's going to be great to see these walls closed up.

An un-glamorous but very important shot of the firestopping.

12 August 2009

one last view

Here's one final image of our radiant floor tubing- they're pouring our slab tomorrow!



You can also see that they've cleared out most of the construction debris in the back yard in preparation for the ipe deck.



The decking will float above the dirt, allowing water to easily reach the roots of the existing tree.

07 August 2009

radiant floor heat

Almost all of the radiant floor tubing has been installed over the last couple of days. After some fine tuning earlier next week the garden floor slab will be poured.




Exterior work at the garden and roof also continues. The retaining walls will be complete by the end of the day.
The view from the upper hvac roof looking down to the new top floor terrace
The new dormer windows look great from the inside and outside. I still can't believe that we were walking on the cornice!

08 October 2008

construction

At last week's meeting we saw a slew of progression on site. Not only was the majority of the interior demolition complete but the second and third floors had almost all of their floor joists in as well as two layers of sub-flooring secured in place. No more jumping from joist to joist to pass through the house! This is a huge plus in my book.

In addition we also observed the initial removal of the rear wall and the new completed rear wall foundation walls. Our meeting this Friday should allow us to see the whole back wall missing with the house completely open to the garden.


Removal of the existing rear wall. To get this close to the edge our contractor had to walk down to the very end of a rather precariously balanced w-flange...




Some shots of the new rear wall foundation wall and its reinforcing bars. See that slight bump out in the first photo where the foundation wall gets thicker at the corner? That's where our steel which is framing out the new rear wall opening will sit. The steel sits in from the facade to allow our re-used bricks to pass in front of it.


Here's the removal of the existing first floor. Those are existing joists to be removed that you can look beyond to see the garden level.